Dec 6, 2007 #1 Arch1234 Civil/Environmental Joined Dec 6, 2007 Messages 1 Location US I client would like to see both the number of working days and overall calendar days. Can I have both? How do I do this?
I client would like to see both the number of working days and overall calendar days. Can I have both? How do I do this?
Dec 6, 2007 #2 IRstuff Aerospace Joined Jun 3, 2002 Messages 44,899 Location US Create a Number1 column. Customize with [finish]-[start]. Result is elapsed days. TTFN FAQ731-376 Upvote 0 Downvote