AccB
Computer
- Sep 19, 2008
- 7
I have a query on the calculation of lateral earth load on a propped retaining wall where the soil height is above the prop. This arises because I suspect that some software I am reviewing gets the calculation wrong but as I’m only a humble computer scientist I thought I’d check that it is not my understanding of the engineering that is at fault.
Take as an example the situation as per enclosed diagram. A retaining wall retains 3m of soil (Soil height, S=3m) and is propped at 2m (Prop height, P = 2m), the wall is idealised as a propped cantilever pinned at 2m and fixed at base and both prop and base are fully braced. Using a simple Rankine model the overall earth pressure on the wall would be a triangular distribution with resultant of magnitude K x S squared x soil unit weight / 2 applied at a height of S / 3 (ie one third of soil height).
However when designing the portion of the wall below the prop - i.e. to determine bending moments, surely only the load on the section of the wall between base and prop is of concern, i.e. the prop carries the load of the upper soil (ignoring load sharing or any mechanisms that transfer load within the cantilever). The total force is the integral of soil loads between base and prop, i.e. the trapezoid as drawn, which gives a resultant which is the equivalent of a soil load of height P (magnitude K x P squared x soil unit weight / 2 applied at height P / 3), plus the load from a uniform surcharge corresponding to 1m of soil (ie magnitude K x 1 x soil unit weight applied at height P / 2). Never mind the magnitude of the resultant from combining these two forces the point of application will be a height somewhere between P / 2 and P / 3.
My point is that it would surely be wrong to use the resultant values calculated from the overall earth pressure on the wall, - the magnitude would be too great (but that’s conservative) however the point of application is also too high, i.e. S / 3, and that’s not conservative. To take it to an extreme if the prop height is less than a third of the soil height (P < S / 3) then using the overall figures would give a resultant applied at a height above the prop – i.e. which implies that there is no earth load on the wall section below the prop contributing to bending moment. Clearly false, I hope.
Is my analysis correct? If not then I’d very much like an explanation of why it is correct to use S / 3 as the height of the resultant to improve my understanding of the engineering!!
Any help much appreciated - you never know you might be using the software...
Take as an example the situation as per enclosed diagram. A retaining wall retains 3m of soil (Soil height, S=3m) and is propped at 2m (Prop height, P = 2m), the wall is idealised as a propped cantilever pinned at 2m and fixed at base and both prop and base are fully braced. Using a simple Rankine model the overall earth pressure on the wall would be a triangular distribution with resultant of magnitude K x S squared x soil unit weight / 2 applied at a height of S / 3 (ie one third of soil height).
However when designing the portion of the wall below the prop - i.e. to determine bending moments, surely only the load on the section of the wall between base and prop is of concern, i.e. the prop carries the load of the upper soil (ignoring load sharing or any mechanisms that transfer load within the cantilever). The total force is the integral of soil loads between base and prop, i.e. the trapezoid as drawn, which gives a resultant which is the equivalent of a soil load of height P (magnitude K x P squared x soil unit weight / 2 applied at height P / 3), plus the load from a uniform surcharge corresponding to 1m of soil (ie magnitude K x 1 x soil unit weight applied at height P / 2). Never mind the magnitude of the resultant from combining these two forces the point of application will be a height somewhere between P / 2 and P / 3.
My point is that it would surely be wrong to use the resultant values calculated from the overall earth pressure on the wall, - the magnitude would be too great (but that’s conservative) however the point of application is also too high, i.e. S / 3, and that’s not conservative. To take it to an extreme if the prop height is less than a third of the soil height (P < S / 3) then using the overall figures would give a resultant applied at a height above the prop – i.e. which implies that there is no earth load on the wall section below the prop contributing to bending moment. Clearly false, I hope.
Is my analysis correct? If not then I’d very much like an explanation of why it is correct to use S / 3 as the height of the resultant to improve my understanding of the engineering!!
Any help much appreciated - you never know you might be using the software...