PRincez
Electrical
- Nov 7, 2006
- 14
I'm working on the above subject and i am wondering how I can apply the two methods during cable sizing activities.
The load, 200A rated, is 350m away from the source with 2 cores per phase (VD issues). Majority of the cable runs are in an electrical cable trend; 20m approximately, runs in a road crossing PVC duct. The electrical package used for cable sizing is Amtech - there isn't an option to simulate the 2 methods, only one method cable be applied. The direct buried method yields a fairly big cable because of the distance and volts drop consideration however using the duct method gives even a far bigger cable. Since the cable is only in the duct for 15m, i am inclined to waive the 15m implication on the cable itself - the heat generated in the duct I reckon will even out and there shouldn't be trips from thermal overload of the cables.
Just want anyone's thoughts on this.
Thanks
The load, 200A rated, is 350m away from the source with 2 cores per phase (VD issues). Majority of the cable runs are in an electrical cable trend; 20m approximately, runs in a road crossing PVC duct. The electrical package used for cable sizing is Amtech - there isn't an option to simulate the 2 methods, only one method cable be applied. The direct buried method yields a fairly big cable because of the distance and volts drop consideration however using the duct method gives even a far bigger cable. Since the cable is only in the duct for 15m, i am inclined to waive the 15m implication on the cable itself - the heat generated in the duct I reckon will even out and there shouldn't be trips from thermal overload of the cables.
Just want anyone's thoughts on this.
Thanks