s0eebuch
Mechanical
- Sep 24, 2004
- 71
All,
One of my local clients has hired my firm to design a waterline replacement project. About 3,000 LF of transite pipe to be replaced with 6-in diameter ductile iron.
At the tie-ins (where the DI meets existing pipe) I am specifying solid sleeve cast couplings (smith-blair or equivalent).
Obviously the proposed water line cannot sit in the same trench as the existing transite. Plus, because the shutdown to make the interconnections must be as short a duration as possible, I must limit the amount of pipe to be installed while the system is offline.
So, my question is this - I show two 45deg. horizontal offsets to meet the existing water line to tie into, but how much pipe can I indicate for the contractor to replace during one shutdown period (usually less than 8 hours)?
I figured around 3 sticks of pipe (at 20 foot long each) for 6-inch diameter pipe is max. But another engineer here has indicated that the contractor would be good if he can get just one stick in the ground and connected.
Anyone have any experience with waterline replacement? The majority of the proposed water line will be in a separate trench along the road RoW away from the transite pipe to be abandoned - but these interconnects are giving me issues.
Thanks.
Ed
One of my local clients has hired my firm to design a waterline replacement project. About 3,000 LF of transite pipe to be replaced with 6-in diameter ductile iron.
At the tie-ins (where the DI meets existing pipe) I am specifying solid sleeve cast couplings (smith-blair or equivalent).
Obviously the proposed water line cannot sit in the same trench as the existing transite. Plus, because the shutdown to make the interconnections must be as short a duration as possible, I must limit the amount of pipe to be installed while the system is offline.
So, my question is this - I show two 45deg. horizontal offsets to meet the existing water line to tie into, but how much pipe can I indicate for the contractor to replace during one shutdown period (usually less than 8 hours)?
I figured around 3 sticks of pipe (at 20 foot long each) for 6-inch diameter pipe is max. But another engineer here has indicated that the contractor would be good if he can get just one stick in the ground and connected.
Anyone have any experience with waterline replacement? The majority of the proposed water line will be in a separate trench along the road RoW away from the transite pipe to be abandoned - but these interconnects are giving me issues.
Thanks.
Ed