jdgengineer
Structural
- Dec 1, 2011
- 748
We are working on a high end residential project with a basement that due to the potential for a perched high water table the geotech has asked that we design the basement for a buoyant condition with water up to 3'-0" from the ground surface. To counteract the buoyancy we investigate retaining walls with heels, helical/micropiles and a really thick matslab. Due to constructability reasons and waterproofing the contractor prefers the thick mat slab option. We have determined that we will need a 4'-0" thick matslab to offset the potential buoyancy caused by the high ground water.
From a structural perspective, we do not need the matslab to be this thick. It's sole purpose is really just weight to offset the buoyancy. We were thinking of a couple of options and I wanted to see if anyone had opinions.
1) Pour a single 48" thick matslab. To meet the 0.0018 reinforcing we would utilize #8 bars @ 8" oc each way top & bottom.
2) Pour two 24" thick matslabs. In this situation we would design the lower 24" matslab as the structural foundation and detail the retaining walls to tie into this matslab. In this scenario we would likely reinforce the lower matslab with #6 @ 10" oc each way top & bottom. We would then pour another matslab ontop with similiar reinforcing (potentially we could omit the bottom layer and only have steel at the top?). All of the interior shearwalls, posts, etc. would land on the top matslab. The top matslab would be doweled into the retaining walls at the perimeter.
Currently, we have our drawing detailed for the first option. The contractor prefers the 2nd option so we are looking at revising the details for this situation. With the second option, I'm trying to decide if I want to even positively connect the two slabs together. My initial plan was to tie everything together, but thinking about it more, I'm not sure if it is really necessary and I think having hooked bars/single legged stirrups, epoxy dowels, etc. would be a fair amount of work and potentially a nuisance with the first pour.
My questions if we went with the two slab option:
1) Would you only include top steel in the top matslab? It's a pretty thick section so I like the idea of top and bottom steel, but I'm not sure what the bottom steel would be doing.
2) Would you connect the two slabs?
From a structural perspective, we do not need the matslab to be this thick. It's sole purpose is really just weight to offset the buoyancy. We were thinking of a couple of options and I wanted to see if anyone had opinions.
1) Pour a single 48" thick matslab. To meet the 0.0018 reinforcing we would utilize #8 bars @ 8" oc each way top & bottom.
2) Pour two 24" thick matslabs. In this situation we would design the lower 24" matslab as the structural foundation and detail the retaining walls to tie into this matslab. In this scenario we would likely reinforce the lower matslab with #6 @ 10" oc each way top & bottom. We would then pour another matslab ontop with similiar reinforcing (potentially we could omit the bottom layer and only have steel at the top?). All of the interior shearwalls, posts, etc. would land on the top matslab. The top matslab would be doweled into the retaining walls at the perimeter.
Currently, we have our drawing detailed for the first option. The contractor prefers the 2nd option so we are looking at revising the details for this situation. With the second option, I'm trying to decide if I want to even positively connect the two slabs together. My initial plan was to tie everything together, but thinking about it more, I'm not sure if it is really necessary and I think having hooked bars/single legged stirrups, epoxy dowels, etc. would be a fair amount of work and potentially a nuisance with the first pour.
My questions if we went with the two slab option:
1) Would you only include top steel in the top matslab? It's a pretty thick section so I like the idea of top and bottom steel, but I'm not sure what the bottom steel would be doing.
2) Would you connect the two slabs?