Alwynb
Mechanical
- Aug 13, 2002
- 23
Hi there,
I have a problem that I need to build a building over a 1200mm deep transmission 150NB gas pipe of 600kPa. The pipe is to ASME B31.8. My plan is to cast only the raft foundation 450mm deep and then wait until the pipe can be rerouted before construction goes further. Local council does not want to allow this. Do I have any leg to stand on?
Regards
I have a problem that I need to build a building over a 1200mm deep transmission 150NB gas pipe of 600kPa. The pipe is to ASME B31.8. My plan is to cast only the raft foundation 450mm deep and then wait until the pipe can be rerouted before construction goes further. Local council does not want to allow this. Do I have any leg to stand on?
Regards