One of the structures on the contract I’m working on is to be constructed with no bearings. This is the first time I’ve encountered such a structure and was wondering is this normal practice?
The bridge consist of a 50m span deck sitting on an arch profile all cast in-situ and monolithically fix to the abutments.
The abutment themselves are 10m high from soffit to finish road level.