ChiefInspectorJeff
Structural
- Nov 10, 2014
- 50
During inspections and plan review I have noticed the engineer allows 8" -12" from the corner holddown anchor bolts to the 2-2x4 chord of a wood SWS.
It seems the moment on the plate which is acting as a cantilever is much higher than designed for.Also the shear is higher than a 2x4 can take( especially on multistory buildings using type 1 SWS.)
Am I off base here? I recall these failures in testing.
Inspector Jeff
It seems the moment on the plate which is acting as a cantilever is much higher than designed for.Also the shear is higher than a 2x4 can take( especially on multistory buildings using type 1 SWS.)
Am I off base here? I recall these failures in testing.
Inspector Jeff