Kene1
Mechanical
- Jul 18, 2012
- 14
We have completed laying a 12'' pipeline in swamp location and pre-commissioning activity is in progress. A caliper pig was launched on the pipeline after the gauge pig was observed to be badly distorted. The caliper pig showed bore restriction in 5 different locations and the contractor commenced repair work at the locations. Anyway, the client advised that work should be stopped until full investigation into the cause of the damage on the pipeline. Please advise on the steps that needs to be taken, thanks.