- 10
I have an existing building and a new building. The new building is to be constructed immediately next to the existing with a fire separation wall between them. They are to be two (2) separate bldgs. The existing bldg is concrete block and steel and new bldg is all steel construction. Each has a separate service at 208/3. The services are 400+ feet apart. Each bldg has a separate water service and grounding electrode system. Is it best to tie the steel structure of the existing and new bldg together? Is it necessary to tie the water mains and grounding electrode systems together or will the steel structure tie suffice?