Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

BOM qty's and sub assembly qtys

Status
Not open for further replies.

bkp80

Mechanical
Aug 7, 2007
3
We currently use autocad, but are trying to move into Solidworks. We build machinery which require serveral parts, some of those parts are then assembled/welded into sub assemblies, then those sub assemlies may be used multiple times on the final assembly of the machine. The way I've started setting up the drawings is with custom properties info for the bom, each part drawing has its own little bom that specifies material, stocksize, process, etc.. Then I make a sub assembly that may use several parts, and that drawing has its own bom that specifies what drawings are needed to make the sub-assembly. Then I want to make the final assembly with its own bom showing how many individual parts, sub-assemblies, are needed to build the final assembly. In autocad usally take the sub assemly prints and issue them to the weldshop to build, in that drawing is a machine qty telling them how many assemlies they need to weld up. With solidworks im trying to let solidworks keep track of the qty's. My question is in my sub-assmbly drawings how do I make solidworks show total number of assemblies required for the final assembly? basically I want the welder to have a print that shows what parts he need to go get off the shelf to build his print, I also want him to know how many of these assemblies he needs to weld up. I know that in the finall assembly drawing that bom would show how many assemblies are needed, based on how many times I used it in the drawing. But I dont know how i could link that qty back to the sub-assembly drawing so they will know how many to build. Sorry for such a long post, but im trying to be very clear on what im needing help with, and someone please tell me if im doing this the hardway and there is a better way to approach this.

Thanks for the help
Brandon
 
Replies continue below

Recommended for you

Check out handlemans post in thread559-150852

One possible problem with doing what you are trying to do, will arise when you re-use any of those parts or sub-assys in other machines. The quantities required may be different. Normally a work order (or manually marked up print) would carry the quantity required information.

[cheers]
 
Could you elaborate on what handleman is talking about, I'm kinda lost about joining the lines and such, I havent been using solidworks very long. Thanks again.
 
Where the sub-assembly drawing seems to report to an upper-level drawing, couldn't you simply supply the welder with the upper-level drawing (which would show the quantity) with the sub-assembly drawing attached for welding purposes?
By doing that, you'd avoid the problem that CBL brought up.

Jeff Mirisola, CSWP
SW '07 SP2.0, Dell M90, Intel 2 Duo Core, 2GB RAM, nVidia 2500M
 
I supose I could attach the final assembly drawing with the weldment drawing, I was just trying to keep it all on one sheet to avoid the shop loosing prints or misreading qtys. Its hard to find responsable workers.

Thanks
 
Brandon,
Would this work?
Put two separate BOM’s onto your one drawing.
We build the 2 different assemblies’, and then put one SolidWorks table BOM not Excel onto the anchor point. Then right mouse click on the second assembly pick table for SolidWorks BOM. You will have to place this somewhere on your drawing by hand.


Bradley
SolidWorks Premim 2007 x64 SP4.0
PDM Works, Dell XPS Intel(R) Pentium(R) D CPU
3.00 GHz, 5 GB RAM, Virtual memory 12577 MB, nVidia 3400
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor