I am a senior in college and for my groups senior design project we are doing repairs on a bridge. For the jacking system we are going to be using a 150ton jack on top of some false work.
So, my question is: what should i use under the false work to support the false work from sinking into the ground once it has the weight of a bridge section on top of it (143ton)
the black area are typical area of where the false work will be erected
So, my question is: what should i use under the false work to support the false work from sinking into the ground once it has the weight of a bridge section on top of it (143ton)
the black area are typical area of where the false work will be erected