OHEcoEng
Civil/Environmental
- Nov 2, 2010
- 32
Hello, all. I am currently working on establishing a connection method for solar thermal collectors to a roof deck.
We're good with the additional dead load, but I am concerned with the proposed attachment method.
Background:
The system consists of two parallel timber "curbs" 6"x12"x 24' long, each weighing approximately 450 lb and spaced at approximately 5.1' apart. The collectors are mounted at a 45 deg. angle between these curbs, and weigh 985 lb when filled with glycol. The curbs sit at a 45 degree angle to 24' 18LH04 joists.
With our 90mph wind speed using ASCE 7-05 horizontal wind pressures, I am looking at around 1900 lb of additional uplift alng the rear curb when considering rotation around the front curb.
The previous engineer approved of simply placing allthread through the timbers, through the 3" deep-rib roof deck, and through some unistrut against the bottom of the decking with bolt and washer. I don't like the idea of a few spot welds resisting this force.
What are your thoughts on this? Anyone know of a (better) established attachment method?
I have spoken with this "structural" engineer once before, and he was very puzzled about what ASCE 7-05 was. I seriously doubt that he gave the attachment method much thought.
The jpg shows how this thing is laid out - decking/insulation is not shown.
Mike
We're good with the additional dead load, but I am concerned with the proposed attachment method.
Background:
The system consists of two parallel timber "curbs" 6"x12"x 24' long, each weighing approximately 450 lb and spaced at approximately 5.1' apart. The collectors are mounted at a 45 deg. angle between these curbs, and weigh 985 lb when filled with glycol. The curbs sit at a 45 degree angle to 24' 18LH04 joists.
With our 90mph wind speed using ASCE 7-05 horizontal wind pressures, I am looking at around 1900 lb of additional uplift alng the rear curb when considering rotation around the front curb.
The previous engineer approved of simply placing allthread through the timbers, through the 3" deep-rib roof deck, and through some unistrut against the bottom of the decking with bolt and washer. I don't like the idea of a few spot welds resisting this force.
What are your thoughts on this? Anyone know of a (better) established attachment method?
I have spoken with this "structural" engineer once before, and he was very puzzled about what ASCE 7-05 was. I seriously doubt that he gave the attachment method much thought.
The jpg shows how this thing is laid out - decking/insulation is not shown.
Mike