Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Assignment of PQR's

Status
Not open for further replies.

GregLamberson

Petroleum
Dec 2, 2006
577
I have a question regarding WPS/PQR's developed by one contractor under API 1104. Can the client provide the PQR's to another contractor working for them (a separate contract and project) without any permissions from the contractor who developed them?

Obviously the contractor that developed them was paid for them so in essence the client has paid for them.

In case you are wondering, they are trying to compress the schedule wherever possible and would like to eliminate the need to do new PQR's by contractor B. A further clarification, it is the same line pipe, from the same mill (from a stockpile).

So again, can these PQR's be "assigned" without permission from the contractor that performed them? Apart from personal opinions, are there any code references that anyone is aware of that would apply?

Greg Lamberson, BS, MBA
Consultant - Upstream Energy
Website:
 
Replies continue below

Recommended for you

Greg,

QW-103 in ASME IX appears to answer this question with a "no".
___________
Each manufacturer or contractor is responsible for the welding done by his organization and shall conduct tests required in this Section to qualify the welding procedures he uses in the construction of the weldments built under this Code, and the performance of welders and welding operators who apply these procedures.
___________

It also states in the QW-103.2 that the records shall be maintained by the manufacturer.

You could use the "proven" procedures to run another duplicate set and thereby eliminate any guess work. My opinion is that the new contractor would have to re-qualify a WPS.

roadapple
 
"Obviously the contractor that developed them was paid for them so in essence the client has paid for them."

I suppose that would depend on the circumstances. In tank and vessel work, the wps/pqr's are developed by the contractor, but normally the same ones are used for a wide range of work, not just for a specific job, and they normally aren't priced out per job.

You might ponder the question of who is held responsible if any problems come up.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor