Army corps of engineers permitting and time for placing a stream in a box culvert

Status
Not open for further replies.

AuEng99

Civil/Environmental
Joined
Sep 22, 2012
Messages
32
Location
US
Does anyone have an estimate on the amount of time and money that would be required to obtain permitting through the Corps on placing 360 feet of stream in two 6' high x 9' wide box culvert? I attached a photo for the project that will be in Georgia.
 
No photo.

Case loads vary. You can try to contact your regional office directly.




--Einstein gave the same test to students every year. When asked why he would do something like that, "Because the answers had changed."
 
Probably 6 to 18 months, depending on NEPA and how simple the project is.
 