Morrand
Electrical
- Nov 29, 2006
- 16
I'm reviewing some of our old distribution system design practices at the moment, and one that I'm looking at has to do with the application of cable limiters on our secondary network. In short, at 208V it calls for cable limiters on all of the main distribution cables, and on services when there isn't enough available fault current to burn a fault clear.
What is odd about this practice is that it contains this phrase: "Limiters shall be installed on the source end of 500 kcmil services except for cable shorter than 15 feet." It goes on to suggest that limiters aren't required on the load end of those cables either, although it doesn't explicitly say that (yet).
I've been going through the references that I have on hand and can't come up with a good, reasonable explanation why short services would not require limiters. Nobody kept any notes in the file to explain why this was originally written in (though we do have the original, typewritten copy from 1972) so I don't have any direct source for this practice. Neither my 1941 Standard Handbook for Electrical Engineers nor our copy of the 1957 EEI Underground Systems Reference Book are helpful in deciphering this particular rule.
Is there any good general reason why a 500 kcmil service lateral that is less than 15 feet from a grid network source to a main switch should not have cable limiters applied to it, when a similar but longer lateral should?
What is odd about this practice is that it contains this phrase: "Limiters shall be installed on the source end of 500 kcmil services except for cable shorter than 15 feet." It goes on to suggest that limiters aren't required on the load end of those cables either, although it doesn't explicitly say that (yet).
I've been going through the references that I have on hand and can't come up with a good, reasonable explanation why short services would not require limiters. Nobody kept any notes in the file to explain why this was originally written in (though we do have the original, typewritten copy from 1972) so I don't have any direct source for this practice. Neither my 1941 Standard Handbook for Electrical Engineers nor our copy of the 1957 EEI Underground Systems Reference Book are helpful in deciphering this particular rule.
Is there any good general reason why a 500 kcmil service lateral that is less than 15 feet from a grid network source to a main switch should not have cable limiters applied to it, when a similar but longer lateral should?