Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations JAE on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Applicable NEC code articles for 2 Emergency generator connections through transfer switch

Status
Not open for further replies.

power2engineer

Electrical
Joined
May 18, 2003
Messages
53
Location
US
Per attached sketch I have 2 code related questions

1) GEN 1 (800KW) Main breaker is more than 25 FT from Gen output Terminals is this acceptable ?

2) When MTS has selected LOAD to be supplied from GEN 2 (350KW) THE GEN 2 power passes through 1200A Breaker located in GEN 1 compartment. IS this allowed?

2_EM_GEN_NEC_mw2cox.jpg
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top