Hello,
I am a mechanical engineer with experience in healthcare in UK.
Recently I have been asked to design operating theatre suites to American standards.
In UK we have clear design guide, HTM 03-01 for theatres being the most relevant. This document provides clear advise on pressure regimes and air change rate for OR, anaethesia room, scrub room etc.
Unfortunately, so far, I have failed to identify/find a similar document for the USA type of OR suites.
Although I have found information in Ashrae for the OR itself, I can not find anywhere air change rates for pump rooms, scrub up, ante-room/ induction rooms.
Similarly nothing about the pressure regime between OR and the above rooms.
I have investigated the following:
-US Dept of veterans affairs site
-Ashrae guides
-HVAC Design Manual for Hospitals and Clinics
The current requirements for the project are for cardiac, orthopaedic and general OR suites but, unfotunately, the Client has not produced room data sheets either.
I would most appreciate your advice on the above based on personal experience or guide me to what documentation could help me to gain the necessary requirements.
Thank you
Michael
I am a mechanical engineer with experience in healthcare in UK.
Recently I have been asked to design operating theatre suites to American standards.
In UK we have clear design guide, HTM 03-01 for theatres being the most relevant. This document provides clear advise on pressure regimes and air change rate for OR, anaethesia room, scrub room etc.
Unfortunately, so far, I have failed to identify/find a similar document for the USA type of OR suites.
Although I have found information in Ashrae for the OR itself, I can not find anywhere air change rates for pump rooms, scrub up, ante-room/ induction rooms.
Similarly nothing about the pressure regime between OR and the above rooms.
I have investigated the following:
-US Dept of veterans affairs site
-Ashrae guides
-HVAC Design Manual for Hospitals and Clinics
The current requirements for the project are for cardiac, orthopaedic and general OR suites but, unfotunately, the Client has not produced room data sheets either.
I would most appreciate your advice on the above based on personal experience or guide me to what documentation could help me to gain the necessary requirements.
Thank you
Michael