mloew
Automotive
- Apr 3, 2002
- 1,073
I would like to get some input on how to ideally handle alternative work schedules. My company works on a 9/80 schedule; 9 hours Monday through Thursday, 8 hours one Friday, and the alternate Friday off. I created a standard calendar with the non-working Fridays identified every fortnight, and adjusted the working time for Monday - Thursday to be 9 hours. I have the calendar displayed to be this calendar. The resources for the company are all referencing this calendar.
When I create tasks, however, the hours are not coming out right. For example, a three day task that starts on Monday will still only register for 24 hours not 27!
I would appreciate any assistance, as I am trying to use Project to estimate resources to manage my time and to produce reliable quotes.
Best regards,
Matthew Ian Loew
m.loew@ssss.com
When I create tasks, however, the hours are not coming out right. For example, a three day task that starts on Monday will still only register for 24 hours not 27!
I would appreciate any assistance, as I am trying to use Project to estimate resources to manage my time and to produce reliable quotes.
Best regards,
Matthew Ian Loew
m.loew@ssss.com