Does anyone know if the rolling average as described in ACI 301 sections 1.6.6 and 1.6.7 apply when the same mix design was being produced at two different concrete plants?
We molded 7 sets of cylinders for a large elevated deck pour, and the 5th set of cylinders we molded came from a truck that was from one plant, and all of the other sets of cylinders we molded came from another plant.
The one set that we made from a different plant was the only one that did not meet the specified f'c.
We molded 7 sets of cylinders for a large elevated deck pour, and the 5th set of cylinders we molded came from a truck that was from one plant, and all of the other sets of cylinders we molded came from another plant.
The one set that we made from a different plant was the only one that did not meet the specified f'c.