Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

653 Section 9.6 Repair of Defective welds 1

Status
Not open for further replies.

FKOK

Mechanical
Jan 13, 2011
4
Does the repair of pitting in shell plate welds , require 100% final radiography per 12.1.3?
 
Replies continue below

Recommended for you

As a 653 Inspector, I would not interpret 12.1.2 to require RT. It is not a full-penn weld, unless the welder 'blows a hole' through the shell while making the pad weld. Additionally, any Lack-of-Fusion would be parallel to the RT film, thus undetctable [RT a phone book, it looks like a perfect wood beam] You might want to call for a UT-thickness scan to determine proper thickness, if a full build-up is not very evident visually.
 
Thank you sir, pardon my ignorance to this media and providing so little info.

We are repairing pitting, primarily in the weld and HAZ area of a 650 tank, the pitting per the metallurgical folk is not preferential to the welds, but build up has been attracted to the welds and the mechanism is being considered under deposit.

We have ( pre- coating application) pt inspected the excavated areas and re-welded with a final PT, prior to flat topping the welding for a lap patches (engineering exempt from 653).

This corrosion has been repaired on approximately 600 linear feet of weld, in a tank with 3000 linear feet of shell welds.

We have one faction interpreting, 653 latest edition, section 9.6, that weld corrosion / repair, is a weld defect and the requirements of 12.1.3, leading to 100% radiography apply.

The other are arguing that only, weld induced flaws , per 9.6.1 require 100 % RT inspection per 12.1.3.

We are currently inspecting the final welds per section 12.2 ( C- repaired weld joints.) RT inspecting a representative sample of each welder.

100% RT seems excessive, what do you guys think.

Thanks in advance!!!! FKOK
 
Corrosion-induced pitting is not a "Welding" flaw of the weld. It is service-related degradation. If the pitting was pre-existing, meaning pitted the day the tank was built, then that would be a flaw repair. The 653 clause refers to weld defects caused during the welding process, not environmental & process corrosion.

100% RT would be rediculous; the original weld was acceptable and without flaws. Additionally, the 100% requirement only applies to full-thickness welds. Your welds are still without internal flaws, just surface pitting. A 100% examination should be concentrated on the surface, as you performed surface welding only. The only methods that make sense are the mandatory 100% Visual Examination, and possibly Magnetic Particle - MT - testing.
 
Thank you DUWE6,

I was sure your explanation would have satisfied our customer, our 653 inspector is saying the same thing. Yet they are not satisfied.

Is there any documentation (interpretations) or means to have API provide arbitration?

They insist that 9.6.4 is a weld flaw and the requirements of 12.1.3.2 apply.

Any additional help would be greatly appreciated!

9.6 Repair of Defective Welds

Types of weld flaws and nonconformance’s that need repair are described in 9.6.1 through 9.6.4.

9.6.4 Welded joints that have experienced loss of metal due to corrosion may be repaired by welding.

12.1.3 Repaired Weld Flaws

12.1.3.2 Completed repairs of butt-welds shall be examined over their full length by radiographic or ultrasonic methods.
 
Your customer may have his 100% RT, if HE pays for it.

Your contract was for a valid 653 repair. Two 653 Inspectors have deemed your repair valid. You have fulfilled your obligation. Please don't let yourself be bullied.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor