rharting
Structural
- Dec 17, 2007
- 41
I'm working on a project where we are checking an existing composite floor system for additional equipment loads. The existing infill beams are W16x26 with only 10 shear studs on them. Given 3/4" dia, weak stud the beam would be less than 25 % composite action. Adding more steel would only make this worse and the owner would like to continue using the floor system.
Questions to all:
a)25% min composite action is a standard practice and in many texts it says that composite action below 25% are not accurate. Is there anything in the code that states the 25% min rule?
b)when determing the moment capacity of the W16x26's without any additional reinforcement, would you consider the less than 25% composite action or simply design it as non-composite?
Thanks to all.
thread507-182835
Questions to all:
a)25% min composite action is a standard practice and in many texts it says that composite action below 25% are not accurate. Is there anything in the code that states the 25% min rule?
b)when determing the moment capacity of the W16x26's without any additional reinforcement, would you consider the less than 25% composite action or simply design it as non-composite?
Thanks to all.
thread507-182835