edward1
Geotechnical
- Dec 27, 2001
- 137
Why would a state DOT bridge engineer demand at least 2 feet of select fill with asphalt on the brige approach if the contractor opts not to pour an approach slab? Is the 2 feet fill a rule of "That's the way we have always done it" or is does it have something to do with impact reduction?