thanks for your insight. I have a master panel and two additional panels connected to master panel. I can saturate one sample using master panel and 6 samples using the other two panels. I also have two geotac pumps to saturate and consolidate samples (these pumps are automated)...
Big H, thanks for your valuable insight. My tests are with pore pressure measurements. I was thinking its going to take one day for saturation, one day for consolidation and one day for shear. Based on my local experience I am pretty sure my samples are highly plastic clays (we haven't drilled...
Hi,
i am working on a geotechnical project. Part of the project consists of running 108 (single samples) consolidated undrained triaxial tests. I need to finish it in 90 calendar days. I am trying to come up with a plan of action.I am wondering how long will it take to run each test...