Hi,
Thanks for your reply. What is time to monitor cold joint for different mix? is there any handy table available? We have difference of tem too; start at -5 and at end +7.
Ron- please corrects me if I understand your second sentence wrong. We pour wall full height at 3mt length. if we do...
Hi,
What is recommended Height of Horizontal joint on 500mm thick and 5.5 mt. high vertical wall of water reservoir?
Or no need of horizontal construction joint.
thanks for your time,
rakesh
Hi,
Is there any thumb rule for Placing Plumbing Pipe in slab?
what are measures and methods take in to account for Hunching desing?
Thanks for you time
rakesh
Hi,
thanks for your time. I am not sure why engineer did control joint(thats the term they use on plan)on Base Slab of 16X24 mt, thick 300mm. that can be doable in one day or one pour.
control joint allow any movment in cocnrete. so is it any any voloumn replationship with tem. that governs...
Hi,
is there any Rules ot Design guidelines for control joint in concrete water reservoire design. Thickness of walls and slab is 300mm. That is in cold weathre expouser too.
thnaks for your time.