  1. t1t2t3

    Sensitive leak testing

    Not every time. You can use sensitive leak test, after hidrotest ( normally in construction phase to ensure the integrity of the line)to check the joints out of test during Hydro, like control valves, conections to vessels, towers, exchangers........(STL normally is used during pre-commisioning...
  2. t1t2t3

    Weld repair after PWHT

    Yes, depending the size of the repair you can apply: 1.- Temper Bead (Half bead) 2.- Weld the repair with IXCONE 182 (Ni Cr 3) or 3.- Repair and new PWHT.
  3. t1t2t3

    QW 410 (WPS)

    Good days. If we have a grove in V to be welded with one GTAW pass in root and three SMAW's passes for landfill: is it necessary to t consider (For the WPS) simple for GTAW and multiple pass for SMAW? Or it is considered to be the total grove without discerning the two welding process...
  4. t1t2t3

    false certs

    What you want to say with " Falsification of welders certificates ". Papers (WPQ) are not according with ASME IX essential variables for welders and for your process? or there are not evidence of testing (Bend Guided or RT)? I do not deal to t What you refer
  5. t1t2t3

    Generic ITP for inductrial construction/fabrication

    There are other variables to have in mind: 1. To elaborate the ITP must have clear the steps of manufacture and the points of inspection required by the codes, specifications and other requirements of the project. 2. To establish the level of inspection (visits, frequency, permanent ....). 3...
  6. t1t2t3

    Generic ITP for inductrial construction/fabrication

    Please be more specific over the construccion/Manufacture to which you refer. The points to be including in a ITP change depending of this initial parameter and also to the code, specs and rules to be applying. The points like HOLD POINTS, Check up documentation or witness depend on what you...
  7. t1t2t3

    Minimun Hardness T-91

    My problem is opposite to the raised one for bob74r. For specification of the client the minimum hardness required after PWHT is 200HBN, nevertheless the values are around 170HBN for welds of T-91 (P5B, now P15 E). In no specification I find (including ASTM) minimun values of hardness after...
  8. t1t2t3

    NDE before and after PWHT

    Totally in agreement with Stanweld. Little more, we can select critical welds by positions of welds, difficult access after welding (Scaffoldings), weld degree of material (5A B for example)..... Sure that NDT before and after PWHT it is not the best desición. A curve showing the cost/ risk for...
  9. t1t2t3

    Pipe Markings

    A53:Specification for pipi,steel, Black and Hot dipped, Zinc Coated, welded and seamless. A106; Specification for seamless carbon steel pipe for High temperature service. A333: Specification forr seamless and welded pipe for Low-Temperature service. API 5L : Specification for line pipe
  10. t1t2t3

    Oil tank

    Sorry, why not API 620?
  11. t1t2t3

    Hard Stamp vs Low stress

    Has any one here information about the damage and consequences coming from the use of Hard Stamp (Weld # and Welder #) instead of Low Stress over ss pipe 304 and 316. I'll stimate your answer
  12. t1t2t3

    Duplex2205 Torquing

    Hi Steve., finally we are using the same Troque table for ss316. Thanks You
  13. t1t2t3

    Duplex2205 Torquing

    I m looking for a table or a Spec. with the bolt torque and bolt force values (Friction coefficient U= 0.10 to =.12). Material: Duplex 2205 (UNS S32205- ASTM 479) Target. To fix an structure cell. I found nothing in Codes, nothing in google........ May be here, get it. Thanks