Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. tedamiao

    Interior non-load bearing CMU wall

    In my opinion, you have to ask contractor to open ceiling to add angles. You may use shot pins for angle to deck attachment.
  2. tedamiao

    Multi-Story Wood Shearwalls

    We use panel blocking to transfer shear. Basically it is four pieces 2x member to form a rectangular shape with sheathing on it. This panel blocking shall be put between floor joists or floor trusses on top of shear wall and under floor sheathing.
  3. tedamiao

    CMU Foundation Walls

    In our office, we always call out fully grouted masonry walls below ground.
  4. tedamiao

    Composite Deck Capacity

    What I did before was same as kslee1000 said. Note allowable capacity given by catalog is superimposed load. You do not need consider slab self weight.
  5. tedamiao

    Extra 2'' concrete on PT slab

    It is elevated slab at basement level. Extra 2'' concrete was on top as topping only.
  6. tedamiao

    Clerestory - Tension Only Bracing

    I do not thick tube steel moment frame is good option. R factor is very low (R=1.5 for tube) and it is super hard to have approved moment connection per current code for tube. Wide flange is first choice if considering moment frame I believe.
  7. tedamiao

    Extra 2'' concrete on PT slab

    Seismic is not a problem since it is at basement level and it can not go anywhere. Light weight concrete is not a choice due to many reasons such as anchor bolts capacity, budget..... Yes, it will take long time to re-analysis. If totally redo it, not only thickness need be changed, but also...
  8. tedamiao

    Extra 2'' concrete on PT slab

    Thanks, guys. I will run analysis to see........It will take a lot of time.......Plus there is no budget for this work. What happened is contractor does not want to change anything.....
  9. tedamiao

    Extra 2'' concrete on PT slab

    Hello, friends, We have finished calculation/drawings and passed plan check for a 10'' thick two way post-tensioned elevated floor slab. Everything is ready for construction. Right now, owner is planning to use 12'' thick and leave all PT cable and mild reinforcing at the same...
  10. tedamiao

    Hillside Design

    It is rock site. Main purpose of caisson is for sliding resitance rather than bearing. Seismic load is big for retaining wall but is doable for concrete wall. Main issue is how can we make house wood construction except retaining wall.
  11. tedamiao

    Hillside Design

    Thanks, Mike and csd72, The diagram was creasted by us and pile will be designed by us as well. Also,please note, we are using Mat foundation (can be 12'' to 24'' thick if needed). Retaing wall will be designed as cantilever wall. What we are trying to do is away from hillside design...
  12. tedamiao

    Hillside Design

    No, it is not soil problem. It is seismic design problem if using hillside design requirements. Most critical problems are wood shear walls can not be used, need design a lot of primary anchors and secondary anchors. Design is tough and of course, construction cost will be increased a lot, a...
  13. tedamiao

    Hillside Design

    This is a tough situation and I hope your experienced engineers can give me a hand. It is 3 story house on hillside (V:H>1:3) in Los Angeles. How can Hillside design requirements section 1666 be waived? I have never done hillside house design. Can we do following (please refer to attached...
  14. tedamiao

    Plastic Section Modulus for Cold Formed Steel Sections

    Nutte, thanks for the input. The thing is for connection design, screws are always control rather than section itself. Also we will not try to make moment connection. Almost every connection was considered as pin connection.
  15. tedamiao

    Warehouse is it a Buisness facility or storage facility?

    My understanding based on experience: It is true that drawings need to be stamped by a P.E. Special inspection may not be needed depends your project structural design information. For example, if you have field weld or epoxy anchor bolts, you do need special inspection.
  16. tedamiao

    Plastic Section Modulus for Cold Formed Steel Sections

    For most cases we have done in our office for past several years, we are using Plastice modulus Z=1.25*S. We have done step by step calculations and found most of C and Z shape (16GA, 14GA, or 12GA) Z > 1.25*S, therefore we selected to use 1.25*S as plastic modulus. If anything wrong or under...
  17. tedamiao

    Concrete Slab Cracks

    Is that possible you have expansive soil on site?
  18. tedamiao

    Built up section modeling

    It is close to property line, only 15' to 20' away. The retaining wall is part of the building (five stories total). We are planing to use 10'' concrete mat foundation. I think soil capacity shall be ok if we following flat pole design to get embedment (could be 50ft or more embedment) by...
  19. tedamiao

    Drift for Moment Frames

    In high seismic zone, like Los Angeles area, it will be really hard to make drift under limit. Strength level, 6x6x1/4 column can work while 6x6x1/2 may still not work by considering drift. Anyone has better ideas to deal with this issue???
  20. tedamiao

    Built up section modeling

    It will take a lot of time to get permission from Caltrans, probably 1 year. For sure, client can not afford this timeline. Perhaps, there are some telephone, electic or other embeded wires overthere, there will be a great chance for tie back cable to hit them.......

Part and Inventory Search