I'm Newbie on MS Project.
The Default calendar is 8h/day but there are resources that need work 10h/day.
I changed the resource calendar but I don't get any change on project. How can I aplly the changed resource calendar?
Thank you very much
Obede
Brazil
Hi dear
I configured the working time to 8 hrs/day and I created tasks with less than 8 hrs.
Why doesn't the milestone duration match the sum of taks?
Thank you very much
Obede
Brazil
Hi,naygoo
I'm reading articles about baseline duration and I think I'll solve the problem. I need to maintain the original value (planned).
Could you tell me where I can get good articles about MS Project.
Thank you very much
Obede
Brazil
Hi, dear
I'm Newbie on MS Project.
I need to create a Collumn similar to Duration Collumn but this collumn needs to maintain fixed values, that is, even when I change the values on Duration Collumn or Actual Duration Collumn this Collumn doesn't change values.
Is it possible?
How can I get it...