Hi
after 3 years of use we need to change our probes (ER,LPR ).
my question is shall we bey all the probe or just the insulator and some o-rings ?
did you extracted probes on pipeline service or at shut down period?
thanks to all helps
the classical case of a feeder MV cable for an impedance Z at L distance.
actually i want to make a program that calculate and i hope enrich it step by step.
thaks
An induction motor has form 5 to 7 time power at starting than in nominal running.
you have a motor: P=110kW -> S=138 KVA at nominal running.
when starting : S=(5to7)x 138 = 690 to 966 KVA needed !it but yoy have just a generator about 480 KW-> 600 KVA.
i thing you need to change the starting...
HI
You can test the two software, by using a known exempel, try a simple circuit with one source and one self (if you want R+jX) but constant R and X.
compare with your calculation note !
still use P.U .
I have to feed Base Camp, power needed 4 MW, 5,5 KV (50Hz, the cable length is 6000 m.
how (formula or the norme) must i choose the cable ?? what is the right steps ???
thanks.