Thank you , There are 3 hrsgs from 4 working each produce 100 MW , the load on the steam turbine is 98 MW and the inlet pressure is 70 bar , the bypass is open in this case and we are on " position control mode " , but on the start up curve , the steam turbine's load of 98 mw requires a pressure...