Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations 3DDave on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. Kareem Eltouny

    Post-drilling for electrical fixtures and utilities effect on tunnel lining segments

    Thanks MotorCity for your help, I've been searching lately (for almost two weeks) for any reference that describes how drilling in concrete affects durability of the tunnel lining without any luck. If you've got any reference (book, paper, article anything) please let me know.
  2. Kareem Eltouny

    Post-drilling for electrical fixtures and utilities effect on tunnel lining segments

    Thanks oldestguy for the website, and thanks MotorCity for the response, does that mean that anchors should be installed after using an instrument to know reinforcement locations first? this will take too much effort for installing fixture in a 5 kilometers tunnel, maybe there is a faster way to...
  3. Kareem Eltouny

    Post-drilling for electrical fixtures and utilities effect on tunnel lining segments

    Greetings, I've a question regarding the post-drilling and post-installation of anchorage / fixtures for utilities in TBM tunnels. Does post-drilling for installing anchors in tunnel lining segments affects durability of the precast segments? as they reduce the concrete cover while drilling...