I saw that table in the 1994 version, but for some reason, I have two big name customers with very similar parts, one aerospace, one medical both saying they don't allow us to add the datum shift when using the concentricity gage, only when checking on a CMM. I wish I knew what they were thinking.
Thank you both very much. I would love to see those examples in the 2009 version, but I only have the 1994 version. Maybe I can get the company to splurge on the new one.
I have two identical holes on center line drilled on opposite ends of a part. One hole is datum A Ø.189/.195 and the other is the feature under consideration, also Ø.189/.195 with a position requirement of φ|Ø.002(M)|A(M)|. We are trying to verify conformance by using the tightest fitting...