Hello!!
I'm working as a piping enginner.
For FW aboveground, galvanized pipes are installed. our procedure to install as follows
1. Cutting and welding pipes to fabricate the spools as per ISOs
2. Make them hot-dip galvanized
3. Install them in the field
When the change of the line is...