Hello,
I have a situation where a steel column (exterior, W12) is leaning due to the foundation heaving about 3/4". The foundation is at least 30 years old, so is the steel. I guess the issue was recently notice by the facilities.
In order to correct the issue "temporarily", the site crew...
I am looking at a 12" cmu wall from 1970s. The drawings appear to show the wall grouted @ 48" oc. I am trying for find some fire rating dates for CMU from that era but not finding anything.
What be a good resource for this information?
Thank you.
I am looking at aprox 13' tall exterior CMU wall. Non-load bearing. Of course it will have to resists lateral loads (likely wind, since its Michigan).
Before I start designing in detail, are there any cmu max height requirements for a cantilever wall?
Thanks,
Single story masonry building with precast roof. Wall height aprox 15', 8" cmu.
My question is about putting the roof (precast planks) on the wall once the wall is complete. How long should the contractor wait before placing the loading the wall with planks.
Thanks.
Consider a 3'x12' deep pier foundation supporting an out door structural column. The contact tor was supposed to pour a pipe within the concrete. The contractor forgot to do that. They are recommending digging down to one side of the pile 9' deep to install the pipe and fill the void with grout...
190'x232' sports arena (single story). Roof is metal deck on steel trusses. The structure itself is concrete a frame (columns wand beams).
The temp range is 90 F. But the project is an area where air-conditioning (heat and cooling) may not be functional.
I can't decide if an building expansion...
Consider a 138kv system with 4" bus for each phase (attached example). In which direction do the SC forces on each bus act? I am trying to figure out if any SC forces will make their way to the foundation or if they cancel out at the beam. Talking to one engineer, he mentioned that the SC forces...
Ducts for secondary (12 KV) running at 90 to each other. At the point of intersection, how much of a separation is recommended and what should the infill be? I saw numbers of 2' to 4' of "fluidized thermal break" but I can't understand why and how this is determined.
Are there any major difference between the latest 2013 California BC and ASCE 7-10 for seismic design? I recall that in the previous codes some of the R values were different between the two but I can't seem to find any differences.
I don't reside in CA and use CBC only occasionally.
I am preparing for these exams but I can't find any example test to figure out the format of the exam. Does anyone know if there are example test references available?
Thanks,
Should any structural bolt have a complete penetration of the nut or is there some leeway to allow not to? I am looking at some structural connections where the bolt doesn't penetrate the nut entirely.
Can a partial capacity be assumed from partial penetration?
I am planning to register as PE in CA. I am currently registered with NCEES so I think that should make things easy. But I am not sure about "California Civil exams in Seismic Principles and on Engineering Surveying". It appears that I can take this computer based test from my home state (IL)...
I have head that term recently and I am not sure if I understand the function and responsibilities of this role. For my information, can anyone share some knowledge. It sounds like its a construction management position.
Has anyone ever heard of TDS (total dissolved solids) for water that can be used for concrete mixture? This is the first time I heard of the term and I am not even sure if I heard it right. It could actually be TDC?
Forgive my ignorance. I alwayws thought water has to be potable but beyoned...