  1. alroum

    STEAM TURBINE BEARING VIBRAITION

    OUR STEAM TURBOSET IS 100 MW, EXTRACTION STEAM, H.P CASE & LOW PRESSURE WITHOUT REHEAT, SAME ROTOR, CONDENSING UNIT, THE ROTOR HAS 6 RADIAL BEARING, B1 BEFORE H.P CASE, B2, B3 AFTER IT, B4 AFTER LOW PRESSURE CASE & B5 AFTER TURNNING GEAR AND BEFORE GENERATOR B6 AFTER IT. ONE YEAR AGO WE...
  2. alroum

    STEAM TURBINE ELECTROHYDRULIC TRIP VALVE

    our plant is 100 mw steam turbine, h .pressure plus low pressure turbine without , some times turbine trip valve partially close during normal operation, trip valve is electohydrulic (DEH) SYSTEM, does any one encounter something like this before?
  3. alroum

    installation of oil vapour extracter fan piping

    I work in steam power plant utility, it's 2*100 MW, we got a heavy oil return from oil vapour extraction system, may be 1 drum every 2 days,the config of system as follow, suction from lube oil tank, include damper then one running and one stand by fan and outlet damper then oil seperator and...