Hi Everyone,
I work for a multi-national company. We're on a large scale extension of one of our chemical plants. We're in the process of removing our main contractor off site for bad performance. The idea was to put our own team of welders and pipe fitters in to complete the job. Completion...
Hi Everyone, does anyone know if there is an acceptance criteria/tolerance for the amount of ditortion one can allow? How would I measure the effects of a heavily distorted branch weld? Does ASME B31.3 or ASME IX address this at all?
Hi Guys/Gals, I want to weld an unassigned material (SANS 300 WA/Boilerplate) to a P1 material (SA 106 Gr B). Do I need to qualify a PQR, or can I use a P1 PQR?
Do any of the ASME Codes discuss material traceability and weld maps as a requirement for Code Data Books? In other words, do contractors have to supply weld history and material maps on their AS BUILT isometrics? Is this required by ASME B31.3?