All,
All the electrical experts, please help me find out some references that talks about overall stability of the system,. Here is what I am fighting with.
We have a potential design that involves two 50MW of power generation at 13.8kv (total 100MW). This power needs to be shipped at a...
All,
All the experts there, has anyone come across with installing 260kv cables buried underground? I am looking at an application where we possibly need to bury cables for a distance of 1.5km.
Few vendors offer 345kv cables suitable for direct burial, can someone help me answer the...
All,
I am looking for technical data, typical vendors, who can or actually have used 15kv, 6000A, 60KA switchgear. I was able to find one at PACS industries, can anyone share me their experience?
Thanks,
Bpn
a 50MW gen at 13.8kv will be located 1.5 km away from the load.
I was wondering if anyone has any experience running U/G and tray rated cables for that long distance. 50MW is a lot of current, about 2700A. The cables we could think are using 1000MCM single conductor aliminum. If we use these, we...