Hi all,
I am a newbie in Hysys. Please offer me some help!
Basically I am trying to tie-in a well's production into an existing flow line(pipeline) from another well. So that two wells will share one common line and go to a satellite location.
I am trying to use HYSYS to determine the...
Hi there,
For piping, usually you do a wall thickness calculation based on CSA z662 or asme b31.3 and you get the minimum wall thickness. Based on that, you select the pipe schedule that is greater than the mim. WT required.
So for pipeline, using CSA z662, you get a min. WT based on the...
Hi all,
I am a newbie in Hysys. Please offer me some help!
Basically I am trying to tie-in a well's production into an existing flow line(pipeline) from another well. So that two wells will share one common line and go to a satellite location.
I am trying to use HYSYS to determine the...