I am working on a 240/144kV transmission line protection, in a Utility, Canada. I am fairly a new protection engineer. The philosophy is as follows:
They are using POTT schemes with the exception of PUTT at generation sites. There's evan a PUTT on one end and POTT on the other.
For short...