Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  • Users: H1H2N3F4
  • Content: Threads
  • Order by date
  1. H1H2N3F4

    Repetative cable failure

    Helo every one: We have around 500m cable that are connecting and backing up ( during maintenance or interruptions) two 4.16 KV systems. This is a BILCA cable that is rated for 5KV and always energized from one side and open in the other side. It is rarely used, however it fails many times in...
  2. H1H2N3F4

    Cause of substation battery dry out

    What cause the substation battery to dry out & what is the impact of adding too much water frequently on the battery life and condition. I have to add water almost every two weeks. H1H2N3F4
  3. H1H2N3F4

    Transformer secondary bushing overheating

    Good morning all. We have a double ended switchgear that is rated for 3000A. This switchgear is supplying power to four ( 4) Gas compressors ( 20,500 hp each) and are continuously running. In addition, this switchgear is being supplied by two 60/80MVA, 69kv/13.8kv Bruch type transformers. My...
  4. H1H2N3F4

    Transformer rating

    Hi every one; I am a new engineer and I have a question to the group; I have a small project where we need a three phase 225 KVA transformer. This transformer size is not available in our yard and the installation is urgent. A friend of mine advised me to use three single phase 75 KVA...
  5. H1H2N3F4

    Transformer laoding

    I have a primary transformer that is a 1500 KVA, 69KV/13.8KV. This transformer is supplying power to different loads total of ( 680 KVA). A request for more power from this transformer was processed with the following specification: Connected load is 1000KVA and the estimated total Demand...
  6. H1H2N3F4

    Parralleling Transformers

    I am reviewing a project where the design contractor is intending to parallel a 30MVA , delta-Y transformer with a 30 MVA Y-delta transformer. I think that this can't be done because of the difference in the angular displacement between the two transformer windings. He insisted that this can...