  1. darkertint

    P3 keeps changing dates

    See the pictures for reference. http://www.primaveratools.com/Portals/4/activeforums_Attach/before.JPG http://www.primaveratools.com/Portals/4/activeforums_Attach/after.JPG Why is it changing the construction activities so they strart at the beggining when they are supposed to be succesors...
  2. darkertint

    How to track sub-activies in Primavera P3?

    I have 2 activies - Pre construction and Construction and there is a bunch of sub-activies for each one. How would I set this up so the critical path of each sub-activity stays with the right activity?