Hi all,
I want to know about shopt inspection plan. I asked the contractor to provide "Marking & Cutting Report, Fit-up Check, Visual Check for Welding". But the contractor said it is not necessary since it is process inspection and the final is already covered in the dimensional and NDE test...
Hi all,
I have problem in reviewing QC document for Pressure reducing desuperheating valve (PRDS)
material: A216 WCC
rating : ASME 600#
Plug and seat ring material: 410 SS (ANSI 410)
my question: i asked for NDE liquid penetrant (PT) test for hard facing area for plug and seat ring material...
Hi all,
I have problem in reviewing QC document for Pressure reducing desuperheating valve (PRDS)
material: A216 WCC
rating : ASME 600#
Plug and seat ring material: 410 SS (ANSI 410)
my question:
1. i asked for NDE liquid penetrant (PT) test form hard facing area form plu and seat ring...