In a pipeline of 28 km, to pass a buried pipe gives me the following error:
"Too many soild supports needed for the model. Please break the model down and use the large include"
How can you do to separate the model number and perform a single analysis?
thanks for the help
Good day,
I am working in the early stages of engineering that consists of two pipelines (API 42 º and 16 º) of approximately 500 km.
I have previously worked with pipelines (gas) in engineering detail.
I have three questions regarding the design in its early stages:
1. The design of the pipe...