This is obviously a no brainer to some. However, my company does work orders from time to time on our projects.
It is confusing to me. How are supplemental agreements related to work orders?
Is there any common rule of thumb with setting the elevation of a pipe invert (where the mitred end exists) with relation to the ditch bottom. I've heard many diferent schools of thought on this. Contractors appear to build the ditch bottoms slightly (approx. 2 tenths of a foot) lower than the...
Recently, there was an employee who persisted that the contractor could not de-water an area unless he applied for a dewatering permit. Is there such a thing? The project already had an existing NPDES permit posted. I thought that the NPDES Permit umbrella's all de-watering; provided that it...