Hi
I need formula which calculate days after one task to the next task? I'd like to put that formula in column. Could you somebody help me?
Example:
milestone - date of delivery product A
task 1 / start date / finish date / number of days between delivery A and start task 1 /number of...
Hello
I'm beginner scheduler in MS PROJECT and I've 3 problems:
1) milestone
when I filled "resorce name" i can't put 100 % in fild "% work complete".
how to resolve it? (when fild resource name is blank it's OK with 100 %)
When I put 100 % in fild "% work complete" (after resolved earler...