Been a while since visiting the forum and glad it’s still top notch.
The issue I’m facing is a 21,300 (-25 degree F) quick chill area devised by (3) insulated metal paneling bays. The ceiling of this area is the walkable flooring of an interstitial space above which will be fully sprinkled...
OK....any of you designers or DP's have any research links to the allowance of ESFR for the protection of an area used for IIIB paint process. There are no issues with ceiling or obstructions or supply. I have racked my brain in research of FM, 13 and UL and can't find any specific allowance...
Up front I apologize if this was covered somewhere else!
Q1: What are some of the typical "approved" and or listed design schemes being used to provide a means for meeting the forward flow testing requirements of 13/25 with system demand and hose stream?
Q2: Will a test of the fire pump at 100...