  1. QuickFlange

    Portable receiver

    HI, We are in the process of designing a 30" crude oil line where the client wants to put a portable scraper trap.Does any one have an idea about portable scraper trap and how it looks (space occupied, etc.,) and the principle of operation. A sketch will help me in understanding. Thanks in...
  2. QuickFlange

    Stress Analysis

    Hi, Can anyone help? 1. For stress analysing flare lines do we need to take care (input) the piping slope while modelling in caesar? 2. Is it possible to input the Autocad dwg file in to caesar directly? 3. Can caesar out put check the pipe thickness for it's sufficiency? Thanks
  3. QuickFlange

    Piping Class Specification

    Hi, I have to prepare a piping class specification for my present project. Can anyone tell me what basic informations are required to start preparing piping class specifications? Thanks
  4. QuickFlange

    PIPELINE PIGGING

    Hello, Can anyone clarify? In line pipes (piggable lines)is it necessary to match pipe ID and the connected valve (or)any other fittings like tee, etc.,exactly with pipe ID? How much difference is allowed? Thankyou.
  5. QuickFlange

    BUTTERFLY VALVE

    Hello, Can anyone tell me what is a high performance butterfly valve? Also what is the meaning of "double offset" & "triple offset" in butterfly valves? What does generally mean by OFFSET? Thanks.
  6. QuickFlange

    HOT TAPPING

    Hello friends, Can anyone give some tips? I have an 8" carbon steel under ground gas line to be hot tapped with a branch size 8". My questions : 1. Underground hottapping is it possible? 2. What precautions necessary to have this underground hottapping?
  7. QuickFlange

    PRESSURE VESSEL DESIGN

    For a drain vessel design (ASME SEC VIII, Div 1) there are 2 vertical pumps to be mounted on 2 nozzles (650 mm dia) on top of this horizontal vessel. Is any special consideration to be given in the vessel design for the pumps coming on top of the vessel?
  8. QuickFlange

    Stress analysis

    i am involved in a job in installing new MSV skid (2 already existing) where 16" bulk header is extended for a length of 15m. Will the pipe needs to be stress analysed? Design temp. 82 deg C. Rating 600#