  1. apriley

    Cantilever RW sliding resistance with shear key

    I'm designing cantilever retaining walls per Caltrans BDS, which gives two different methods for calculating sliding resistance when shear keys are present (see attached). The first assumes a horizontal failure plane at the bottom of the key. For this, my sliding FS is OK. The second method...
  2. apriley

    Differential Deflection in RCB

    We're adding fill to an existing rcb at the end (existing fill tapered to 0 at the end, and we're putting 14' on it to match the rest of the existing). The geotechs are telling us that the settlement will be 3" on that section. The lead structural engineer on the project is worried about...
  3. apriley

    Barrier slab design with sound wall

    I am checking an MSE wall with a barrier slab that supports a sound wall. The Caltrans detail uses an 8' barrier slab with a CIDH pile to resist these seismic and winde loads on the wsound wall.However, it is unclear to me what deisgn methodology should be used. The designer assumed that the...
  4. apriley

    Traffic barrier on MSE Wall

    I have seen previous posts about MSE walls with barriers, but I still need clarification. Currently, Caltrans requires the use of BDS LFD for MSE wall design in lieu of AASHTO LRFD. Caltrans requires designing the moment slab and top row of MSE reinforcement for traffic impact. However, it is...
  5. apriley

    MSE Wall with traffic barrier and moment slab

    I have seen previous posts about MSE walls with barriers, but I still need clarification. Currently, Caltrans requires the use of BDS LFD for MSE wall design in lieu of AASHTO LRFD. Caltrans requires designing the moment slab and top row of MSE reinforcement for traffic impact. However, it is...