Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  • Users: demayeng
  • Content: Threads
  • Order by date
  1. demayeng

    Certifying existing building

    We've been asked to look at a suspended concrete floor in an existing building (built around 1980) to advise on load capacity. There are no existing drawings available. Out of interest, how would this process occur? If the client does happen to find some drawings, I could analyze it no problem...
  2. demayeng

    Has anyone got a simple soldier pile retaining wall design method?

    I am looking for a simplified design method for a soldier pile wall. I have the more complex ones that require iteration, but i was once taught a much simpler version, that I have since forgotten! It is just for small walls Thanks very much
  3. demayeng

    Carpark collapse - Sydney

    Another one to follow, not much information as yet.. http://www.smh.com.au/nsw/car-park-collapses-at-sydney-shopping-centre-20120724-22loz.html
  4. demayeng

    Re-shoring / backpropping (again)

    Another question about backpropping of a suspended slab (not in a multistorey building) It appears to be common practise around here to strip formwork after a number days and replace with backprops. I have seen backprops at much fewer (at greater centres) than the props that were holding up the...
  5. demayeng

    Structural bonded topping surface preparation

    Is a raked finish suitable (for the longitudinal shear connection) on a precast slab panel with a structural topping?
  6. demayeng

    Lateral restraint for top of needle beam props

    Hi, I am having trouble visualizing this.. I got this image off a prop-hire business website Is that ok as pictured, or do you need to laterally restrain the top of the props? Thanks
  7. demayeng

    Tilt up panel repair

    Hi, my question is whether is possible to repair a damage tilt up panel in situ.. The building is a steel portal frame factory approximately 6.2m tall at the apex, on the gable end 2 panels have been damaged by a truck impact, damage is below 2.5m height. The panels are 3m wide each and span...
  8. demayeng

    Do composite metal decks upset MRI machines?

    Has anyone done a suspended slab under an MRI with composite metal formwork? Thanks
  9. demayeng

    Failure of concrete block retaining wall due to starter bar corrosion

    Hi, We have recently seen a cantilevered concrete block retaining wall fail due to corrosion of the starter bars at the base of the stem where it joins the footing. We have considered galvanized starter bars for these types of walls as a result, however predictably most builders have a problem...
  10. demayeng

    Concrete filled brick retaining - wall max height

    Hi, I've been told there is a maximum height of 1100mm (3ft something) on brick retaining walls (2 brick skins with a 100mm concrete filled cavity). I think it has to do with deflection, however I'm not sure. Does anyone else know why this is and if it's true? I guess there is an issue with...
  11. demayeng

    Soldier pile retaining wall in clay - undrained or drained?

    Hi, I am designing a maximum 2m high soldier pile (steel H sections) in clay. It is a replacement for a similar wall that has rotted out. I don't know anything about the clay except that it is 'good and firm', and that the retained soil has water delivered to it from an uphill property. I am...
  12. demayeng

    Flat roof deflection causing ponding

    Hi, I have to do an analysis on a flat roof that is deflecting and has a pond at the lower end full of water rusting through the roof sheet. The purlins are 200x47 oregon spanning up to 7.5m (so they are undersized already). The roof sheet is deep profile (Kliplok here in Australia) with 41mm...
  13. demayeng

    AS3600-2009

    Hi, This is actually from previous versions of the code also, however Cl 8.1.10.4 (b) says that 1/4 of the midspan positive reo "shall continue past the near face of the support" How come there is no distance prescribed? what does this mean? does 0.1mm past the face comply? Thanks
  14. demayeng

    AS2699 brick ties

    Does anyone have a copy of AS2699? If I am given a 'characteristic capacity' in kN of a brick tie by the manufacturer, what is the phi factor I would apply to this to get my design capacity? I assume this would be in AS2699?? I am a bit over buying codes and then not finding the info i was...
  15. demayeng

    Shrinkage cracks? photo

    Hi, This photo shows a repair in a carpark slab on ground. Apparently a water hydrant line failed under this point so the builder saw cut a hole, fixed the pipe and did this repair. You can see there are radiating cracks out from the hole. I am assuming this is due to a release of shrinkage...
  16. demayeng

    AS3600 concrete strength for slab on ground

    Hi, Nice easy Friday arvo question.. AS3600 is clear in saying that for exposure classification B2 (above ground exterior within 1km of coast) you must use 40 MPa concrete. Does 'above ground' apply to slabs on ground? At this office (my first structural workplace) this is common for...
  17. demayeng

    Re-entrant corners in suspended slabs

    Hi, In slabs on ground, we put in diagonal bars at re-entrant corners to prevent shrinkage cracks propagating from the stress concentration at the corner. With re-entrant corners in suspended slabs (say a 90 degree wall under) there is a similar stress concentration due to the bending under...

Part and Inventory Search