Hi Friends,
I am working on a project where the inside temperature set point for cooling and heating is required to be set at 75 deg F. This is for an Electrical building which houses electrical and controls panels/cabinets Industrial application . Ambient in winter is 30 deg F. The software...
Friends,
ASHRAE provides design temperatures for 0.4%/1.0%/2.0% (Cooling), 99.6%/99.0% (Heating) annual cumulative frequency of occurrence. Are there any guidelines or criterion available to decide what frequency of occurrence should be used for a projects?
Thanks
Hello friends
I am working on the design of HVAC system for electrical buildings for a industrial project located in Louisiana. Does the HVAC design required to be in compliance with energy code (ASHRAE Standard 90.1-2007 and is it required to use COMcheck tool?
Per attached snap snapshot from...
Friends,
Is there any way to enter user defined over all U-value in HAP? In our project, Overall U-value is already defined in architectural specification.
Thanks
Hello Friends
Are there any guidelines in National Building code or ASHRAE regarding maximum Face Velocity or free air velocity for air transfer grilles on doors/undercuts
Firends
Could someone please guide me how to size or select the chemecial dosing/feeder/pot tank on a closed chilled water loop. Plant size is 67 tons
Thanks
Hi friends
I am working on a project where I have to calculate pressure drop across a valve.
Data is as follows
Media: Air at 350 deg C
Flow : 26000 CMH
Valve : 600 dia
Valve Kv : 1839 m3/hr-bar
Air is being forced into the valve by an axial fan having discharge pressure of 100 mm of WG
Thanks
Friend
Can someone directs me to the ASHRAE chapter or any other code where I can find any reference to recommended air velocity in the exhaust duct connected to Kitchen hood. Air will have oil/grease.
Thanks
Guys please help
Is there any requirement in Lloyd rule for Galley ventilation on mobile semi
I am looking for any requiremenys of air changes etc..
Thanks
Hi Friends
Is it allowed to connect exhaust from toilets/washrooms and gymnasium on a common exhaust duct.
On the project that we are working, we are required to exhaust all the air supplied to gymnasium.
I am wondering if we can connect gym. exh. with cabin toilet exh.
Are there any...
Hi Friends
I am reviewing load calcutions submitted by a vendor
Application is comfort HVAC for Living Quarter on an offshore Rig.
There are about 90 small rooms being served by a large common AHU
Vendor has divided the load for rooms into two groups
In group 1, about 40 rooms and in group 2...
Hi Friends
I have been asked to check how the system will perform if 25% of the cooling capacity is lost.
The system is in design stage and the system sizing considering all units operating is as follows
Plant Configuration : 4 x 125 KW
Ambient : 44 deg C/90% RH
Installed Total Load : 500000...